Enotrac carried out the entire implementation planning for the high-voltage and medium-voltage systems (outdoor installations, cable installations), the earthing, the auxiliary systems and the cabling of the control technology. This included preparation of the documents required for the production of the auxiliary power distribution systems (50 Hz and 110 VDC).
Enotrac’s core tasks also included coordination with SBB regarding the primary and secondary components provided by SBB. Other tasks in the project included construction supervision, quality assurance, safety-oriented testing, scheduling, preparation of the final documentation and representing the overall project manager on behalf of the contractor.
In this project, Enotrac was able to make significant contributions to finding quick and safe solutions to emerging challenges thanks to the team’s extensive experience in the field of SBB substations.
-
Client
ERNE AG Bauunternehmung
-
Period
2021 – 2023
-
Location
Delémont, Switzerland
Our services in the project